The dozer rests from a hard day of road building. |
Building the road down the canyon to the Christine Marie claim following the old cat track took me two years -- or two mining seasons (about 2 months). It could have been done faster but I was ignorant and inexperienced both with the intricacies of running my new-old D-4 dozer and working on such steep terrain.
Making the switchbacks was difficult because of the amount of material necessary to push out of the rock slides to make a turn wide enough for a vehicle. In some cases there just wasn't enough rock available to create a smooth turn.
Notice the only level road at Morrisonite running down the cliff on the left. |
On one descending stretch between switchbacks I saw the opportunity to lessen the steepness of the descent by extending the length of the section and making the next switchback up against the cliff on the far side. I started pushing rock onto the old cut slowly raising the new road above the old one. I was encountering many large rocks and moved the Dozer over one that just happened to fit snugly between the tracks of the machine. Beyond it the ground was softer and the Dozer slipped down allowing the rock underneath to crush the oil pan which promptly drained its contents.
Agate and Jasper mining is financially risky in the extreme. There is no way to measure or predetermine the quality (value) of the material before it is extracted. A gold deposit can be measured and essayed to estimate the value that could be produced. This value can be compared with the estimated cost of mining and a profit projected. This is not possible with an agate or jasper deposit. For this reason most agate and jasper mining operations are conducted with minimal investment and lots of ingenuity, persistence, and the necessity to solve problems with what you have.
The dozer was tilted downward about 25 degrees -- the slope of the road. The left track was against the rock slide and the blade had a pile of rock in front of it. The whole machine was in kind of a hole with big rocks behind it that I had just traveled over. There was no access to the undercarriage.
Two of the switchbacks on the new road. |
Jake was working a few switchbacks above me so I walked up to consult with him. After looking over the situation he wryly suggested I could hire a helicopter to lift the dozer out of the hole and put it up on top where I could work on it!
I have always been amazed and comforted by Jake's ability to suggest multiple solutions to any mining problem. He approaches mining problems with optimism, enthusiasm, and the widest range of possibility. Many times ridiculous or impractical solutions clarify what needs to be done and moves the mind away from a negative situation to a more positive direction.
I dug out the Dozer with a pick and shovel until I could crawl under it. I then carried my tools down from the cabin (600 ft. above) and removed the oil pan. I carried it up to the cabins, cleaned it, and JB-welded it together. Once the epoxy was set, I reinstalled it, put in new oil, got the machine running, and went back to work on the road (about a three day process altogether).
A quick note on mining supplies: duct tape, wire, JB weld, and some rubber -- which in my case is old inner tube, because you never know when you might need to make a new seal -- should always be close by.
The dozer rests in Old Boot Dig on the Christine Marie mine for lunch. |